Baruch Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Baruch Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,544,000
Funding Sources:
  • Mayoral
  • City Council

Location

Baruch Playground , Manhattan
Baruch Place and Rivington Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/16/2018