Baruch Playground Comfort Station Reconstruction
-
100% complete
-
100% complete
-
96% complete
This project will reconstruct the comfort station at Baruch Playground.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: December 2015
Projected Completion Date:
January 2017
Completion Date:
January 2017
Procurement
Start Date: January 2017
Projected Completion Date:
October 2017
Completion
Date:
May 2018
Construction
Start Date: August 2018
Projected Completion Date:
January 2020
Adjusted Completion
Date:
April 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Baruch Playground
, Manhattan
Baruch Place and Rivington Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/26/2021