Baruch Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Baruch Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Adjusted Completion Date: May 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Baruch Playground, Manhattan
Baruch Place and Rivington Street, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/16/2018