Baruch Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will reconstruct the comfort station at Baruch Playground.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: January 2020
Adjusted Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,865,000
Funding Sources:
  • Mayoral
  • City Council

Location

Baruch Playground , Manhattan
Baruch Place and Rivington Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/29/2020