Inwood Hill Park Nature Center Sewer Connection Construction

  • Design
    100% complete 
  • Procurement
    85% complete 
  • Construction
     

This project will install approximately 600 LF of sewer line connecting the Nature Center and the DEP Sewer main at 218th street.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date:August 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date:October 2016
Adjusted Completion Date: April 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Sources:
  • Mayor
  • City Council

Location

Inwood Hill Park, Manhattan
Inwood Hill Park between Henry Hudson Parkway and Indian Road intersection with 218th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/24/2017