Inwood Hill Park Nature Center Sewer Connection Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a sewer line between Inwood Hill Nature Center and West 218th Street.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: August 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: March 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $787,000
Funding Sources:
  • Mayoral
  • City Council

Location

Inwood Hill Park , Manhattan
Indian Road and West 218th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project