Albano Playground Handball Court and Multi-Purpose Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the play equipment, safety surfacing, handball courts, and asphalt multi-purpose play area and construct a new spray shower at Albano Playground,

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: August 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Vincent F. Albano Jr. Playground , Manhattan
2nd Avenue between East 29th Street and East 30th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/17/2018