Seravalli Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort station at Seravalli Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: March 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,700,000
Funding Source: City Council

Location

Corporal John A. Seravalli Playground , Manhattan
Hudson Street between Gansevoort Street and Horatio Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/18/2019