Seravalli Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    24% complete

This project will reconstruct the comfort station at Seravalli Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2014
Projected Completion Date: March 2016
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $825,000
Funding Source: City Council

Location

Corporal John A. Seravalli Playground , Manhattan
Corporal John A. Seravalli Playground located on Hudson Street between Gansevoort Street and Horatio Street.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/17/2018