Marcus Garvey Park Fire Watchtower Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fire watchtower and surrounding plaza in Marcus Garvey Park.

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: October 2015
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $7,970,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Marcus Garvey Park , Manhattan
Madison Avenue at East 122nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/05/2020