Belt Parkway Landscape Restoration and Tree Planting at Gerritsen Inlet

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    41% complete

This project will restore the landscape elements along the Belt Parkway and plant trees at Gerritsen Inlet to retain stormwater at these locations.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: September 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: December 2019
Projected Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $7,356,000
Funding Source: Mayoral

Location

Belt Parkway/Shore Parkway , Brooklyn
Belt Parkway between Flatbush Avenue and Knapp St

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020