Belt Parkway Landscape Restoration and Tree Planting at Gerritsen Inlet

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will restore the landscape elements along the Belt Parkway and plant trees at Gerritsen Inlet to retain stormwater at these locations.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: September 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Belt Parkway/Shore Parkway , Brooklyn
Belt Parkway between Flatbush Avenue and Knapp St

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/14/2018