Belt Parkway Landscape Restoration and Tree Planting at Gerritsen Inlet

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore the landscape elements along the Belt Parkway and plant trees at Gerritsen Inlet to retain stormwater at these locations.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: August 2014
Projected Completion Date: September 2016
Adjusted Completion Date: June 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Belt Parkway/Shore Parkway , Brooklyn
Belt Parkway between Flatbush Avenue and Knapp St

 

Project Staff

Contact NYC Parks about this project

Last updated: 05/21/2018