Joseph Austin Playground Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will reconstruct the synthetic turf ballfield and drainage system at Joe Austin Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: March 2016
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: July 2017

Construction

Start Date: August 2017
Projected Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $2,449,000
Funding Source: Mayoral

Location

Joseph Austin Playground , Queens
Located at the intersection of The Grand Central Parkway and 164th Place and 168th Street, Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/23/2018