Brownsville Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the interior and infrastructure of the Brownsville Recreation Center.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: June 2016
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Brownsville Playground , Brooklyn
1555 Linden Boulevard Brooklyn, NY. Intersection of Linden Boulevard and Mother Gaston Boulevard

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/20/2018