Bronx, Manhattan and Queens Reforestation FY15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive species and plant new trees in the Bronx, Manhattan and Queens.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: August 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: June 2015

Construction

Start Date: April 2015
Projected Completion Date: October 2017
Completion Date: October 2017

Understand how we build parks.

Funding

Total Funding: $1,318,000
Funding Sources:
  • Mayoral
  • Private

Locations

  • Fort Totten Park , Queens
    Fort Totten, Cross Island Parkway, Totten Road to 15 Road
  • Pelham Bay Park , Bronx
    Bruckner Boulevard, Eastchester, Hutchinson
  • Soundview Park , Bronx
    Bronx River, Lafayette, Metcalf, Bronx River Avenues
 