Lost Battalion Hall Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Lost Battalion Hall Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: June 2022
Projected Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $18,505,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Lost Battalion Hall Recreation Center , Queens
Queens Boulevard between 62nd Avenue and 62nd Drive

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 06/30/2022

Was this information helpful?