Lost Battalion Hall Recreation Center Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Lost Battalion Hall Recreation Center.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Lost Battalion Hall Recreation Center , Queens
Queens Boulevard between 62nd Avenue and 62nd Drive

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/16/2018