Tony Dapolito Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    51% complete

This project will reconstruct Tony Dapolito Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $16,943,000
Funding Source: Mayoral

Location

Tony Dapolito Recreation Center , Manhattan
Clarkson Street and Seventh Avenue South

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/25/2021

Was this information helpful?