Tony Dapolito Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Tony Dapolito Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $7,042,000
Funding Source: Mayoral

Location

Tony Dapolito Recreation Center , Manhattan
Clarkson Street and Seventh Avenue South

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/25/2020