Tony Dapolito Recreation Center Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Tony Dapolito Recreation Center.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: June 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Tony Dapolito Recreation Center , Manhattan
Intersection of Clarkson Street and Seventh Avenue South, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/24/2018