Tony Dapolito Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    72% complete

This project will reconstruct Tony Dapolito Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: June 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: September 2019

Construction

Start Date: September 2020
Projected Completion Date: March 2022
Adjusted Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $16,942,000
Funding Source: Mayoral

Location

Tony Dapolito Recreation Center , Manhattan
Clarkson Street and Seventh Avenue South

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?