Hansborough Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: March 2022

Procurement

Start Date: March 2022
Projected Completion Date: December 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • City Council
  • Mayoral

Location

Hansborough Recreation Center , Manhattan
35 West 134th Street between Lenox Terrace and 5th Avenue.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/01/2022