Hansborough Recreation Center Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: March 2020
Projected Completion Date: March 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Hansborough Recreation Center , Manhattan
35 West 134th Street between Lenox Terrace and 5th Avenue.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/30/2021

Was this information helpful?