Hansborough Recreation Center Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool, entrance and interior spaces of the Hansborough Recreation Center.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: March 2020
Projected Completion Date: March 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Hansborough Recreation Center , Manhattan
35 West 134th Street between Lenox Terrace and 5th Avenue.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/07/2020