Sunset Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct part of the Sunset Park Recreation Center.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Adjusted Completion Date: February 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Sunset Park , Brooklyn
7th Avenue between 41st Street and 44th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/15/2018