Sunset Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct part of the Sunset Park Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Sunset Park , Brooklyn
7th Avenue between 41st Street and 44th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project