St. Mary's Park Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct St. Mary's Park Recreation Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: September 2017
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $8,320,000
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 145th and East 147th Streets.

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 07/05/2022

Was this information helpful?