Clove Lakes 5K Running Trail Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    18% complete

This project will construct a 5K running trail, including re-grading of an existing trail, new edging, new surfacing and associated landscape improvements in Clove Lakes Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Construction

Start Date: April 2018
Projected Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $1,416,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Clove Lakes Park , Staten Island
Clove Lakes Park, Staten Island, bounded by Slosson Avenue, Victory Boulevard and Clove Road.

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 10/18/2018