Bronx General Site Work (XG-514M)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    95% complete 

This project will reconstruct parks, playgrounds and site work at various sites in the Bronx.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2014
Projected Completion Date:June 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date:June 2015
Completion Date: August 2015

Construction

Start Date: September 2015
Projected Completion Date:March 2017

Understand how we build parks.

Funding

Total Funding: $2,178,000
Funding Source:Mayor

Locations

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/13/2017