Crotona Park Wall and Fence Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    3% complete

This project will demolish and reconstruct the steel fence and perimeter wall at Crotona Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: February 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: May 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $2,366,000
Funding Source: Mayoral

Location

Crotona Park , Bronx
Fulton Avenue bewteen East 172nd and East 173rd Streets at the swimming pool in Crotona Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 09/21/2018