St. John's Recreation Center HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct the boilers and HVAC systems at St. John's Recreation Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: June 2016

Construction

Start Date: December 2016
Projected Completion Date: December 2017
Adjusted Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $3,090,000
Funding Source: Mayoral

Location

St. John's Recreation Center , Brooklyn
Prospect Place between Troy and Schenectady Avenues, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/20/2018