St. John's Recreation Center HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    21% complete

This project will reconstruct the boilers and HVAC systems at St. John's Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: June 2016

Construction

Start Date: December 2016
Projected Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $3,090,000
Funding Source: Mayoral

Location

St. John's Recreation Center, Brooklyn
Prospect Place between Troy and Schenectady Avenues, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2017