Manhattan Oil to Gas-Fired Burner Conversion (MG-814M)

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This multisite contract will convert oil-fired burners and boilers to natural gas-fired systems at various parks and recreation facilities in Manhattan.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline


Start Date: April 2014
Projected Completion Date: October 2014
Completion Date: August 2017


Start Date: August 2017
Projected Completion Date: May 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Less than $1 million
Funding Source: Mayoral



Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/21/2018