Manhattan Oil to Gas-Fired Burner Conversion (MG-814M)

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This multisite contract will convert oil-fired burners and boilers to natural gas-fired systems at various parks and recreation facilities in Manhattan.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: October 2014
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018
Adjusted Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral