West Farms Park Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct West Farms Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: December 2014
Projected Completion Date: March 2015
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: March 2017
Adjusted Completion Date: January 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council
  • State
  • Federal

Location

West Farms Rapids , Bronx
Along the western bank of the Bronx River between East Tremont Avenue and East 180th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/14/2018