Bronx General Site Work (XG-315M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the concrete sidewalks and complete other related site work at various locations in the Bronx.

Project Timeline


Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: May 2015


Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: May 2016


Start Date: June 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Understand how we build parks.


Total Funding: $1,170,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council



Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 03/16/2018