NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Harris Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will reconstruct the park's perimeter lawn area, construct four (4) sets of steel signage, and construct a storm sewer connection.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: June 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: October 2016

Construction

Start Date: February 2017
Projected Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $788,000
Funding Source: Mayoral

Location

Harris Park, Bronx
Harris Park located between Goulden and Paul Avenues and West 205th Street and Bedford Park Boulevard

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?