Paerdegat Athletic Center Air Conditioning Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    82% complete

This project will reconstruct the air conditioning equipment.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: January 2015
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $2,664,000
Funding Source: Mayoral

Location

Paerdegat Basin Park, Brooklyn
PAERDEGAT AVENUE NORTH, BETWEEN PAERDEGAT 13TH STREET AND SEAVIEW AVENUE, Borough of BROOKLYN

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/16/2018