Paerdegat Athletic Center Air Conditioning Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    97% complete

This project will reconstruct the air conditioning equipment at Paerdegat Athletic Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: January 2015
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $2,664,000
Funding Source: Mayoral

Location

Paerdegat Basin Park , Brooklyn
Paerdegat Avenue North between Paerdegat 13th Street and Seaview Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2018