Manhattan General Site Work (MG-714MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will reconstruct pavements, fencing, fountain, planting and general site work in Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2014
Projected Completion Date: April 2015
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: December 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $2,294,000
Funding Sources:
  • Mayoral
  • City Council

Locations

  • Jackson Square , Manhattan
    8 Ave. To Greenwich Ave., Horatio St.
  • Jane St. at 8th Ave.
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/10/2018