Manhattan General Site Work (MG-914MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct adult fitness equipment and reconstruct the basketball court and handball court wall at Booker T. Washington Playground, reconstruct the playground at Chelsea Park, and construct adult fitness equipment and reconstruct the basketball half-court at Columbus Park.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2019
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $2,732,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/28/2020