Manhattan General Site Work (MG-914MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    70% complete

This multi-site contract will reconstruct pavements, fencing, safety surfacing, play equipment, and construct handball courts and general site work in various locations in Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: March 2016

Procurement

Start Date: March 2016
Projected Completion Date: December 2016
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,201,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/15/2018