Little Red Square Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will reconstruct Little Red Square with new pavements, curb alignments, seating, and plantings.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2014
Projected Completion Date: December 2016
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: August 2018

Construction

Start Date: March 2019
Projected Completion Date: March 2020
Adjusted Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $1,742,000
Funding Sources:
  • Mayoral
  • City Council

Location

Little Red Square , Manhattan
6th Avenue between Bleecker Street and West Houston Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/29/2020