Broadway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct landscapes, pavements, fences and benches at several malls along Broadway from West 102nd to 104th Streets and from West 137th to 139th Streets.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: September 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Adjusted Completion Date: September 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Broadway Malls , Manhattan
    Broadway, Columbus Circle to West 110 Street
  • Broadway Malls , Manhattan
    Broadway, West 110 to West 122 Streets
  • Broadway Malls , Manhattan
    Broadway, West 135 Street to West 156 Streets
 