Broadway Malls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    47% complete

This project will reconstruct landscapes, pavements, fences and benches at several malls along Broadway from West 102nd to 104th Streets and from West 137th to 139th Streets.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: September 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Adjusted Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $1,576,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Broadway Malls , Manhattan
    Broadway, Columbus Circle to West 110 Street
  • Broadway Malls , Manhattan
    Broadway, West 135 Street to West 156 Streets
 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/22/2020