St. Gregory's Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct St. Gregory's Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: November 2015
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $1,103,000
Funding Sources:
  • Mayoral
  • City Council

Location

St. Gregory's Playground , Manhattan
West 90th Street between Amsterdam and Columbus Avenues

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/17/2018