NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Van Cortlandt Park Basketball Court and Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    17% complete

This project will construct a basketball court and skate park in Van Cortlandt Park.

Project Update: This project is in active construction.

Project Timeline


Start Date: November 2013
Projected Completion Date: June 2015
Completion Date: August 2015


Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: November 2016


Start Date: February 2017
Projected Completion Date: February 2018

Understand how we build parks.


Total Funding: $1,000,000
Funding Source: City Council


Van Cortlandt Park , Bronx
Van Cortlandt Park


Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 03/16/2018