Van Cortlandt Park Basketball Court and Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    17% complete

This project will construct a basketball court and skate park in Van Cortlandt Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: June 2015
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: November 2016

Construction

Start Date: February 2017
Projected Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Source: City Council

Location

Van Cortlandt Park, Bronx
Van Cortlandt Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2017