Ferry Point Park West Comfort Station Construction - HVAC

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will install the HVAC work in connection with the construction of a comfort station at Ferry Point Park West.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2006
Projected Completion Date: February 2014
Completion Date: May 2014

Procurement

Start Date: May 2014
Projected Completion Date: February 2015
Completion Date: July 2015

Construction

Start Date: July 2016
Projected Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $45,000
Funding Source: Mayoral

Location

Ferry Point Park, Bronx
Ferry Point Park West CS

 

Related Projects

Total Funding for These Related Projects: Between $3 million and $10 million
Funding Source: Mayoral

Project Phase
Ferry Point Park West Comfort Station Construction Construction
Ferry Point Park West Comfort Station Construction - Electrical Construction
Ferry Point Park West Comfort Station Construction - Plumbing Construction

Project Staff

Project Liaison: Michelle Martell