Greencroft Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Greencroft Playground.

Project Update: Contract documents are under review.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Adjusted Completion Date: January 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Greencroft Playground , Staten Island
Located at Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue, Borough of Staten Island.

 

Project Staff

Project Liaison: Charles Fall