Greencroft Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the comfort station at Greencroft Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Adjusted Completion Date: January 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Greencroft Playground , Staten Island
Located at Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue, Borough of Staten Island.

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 08/15/2018