Greencroft Playground Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    12% complete

This project will demolish the existing comfort station and construct a new comfort station at Greencroft Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: October 2019

Construction

Start Date: December 2019
Projected Completion Date: June 2021
Adjusted Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $3,301,000
Funding Sources:
  • Borough President
  • City Council

Location

Greencroft Playground , Staten Island
Greencroft Avenue Between Redgrave Avenue and Ainsworth Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/25/2020