Travers Park and Staunton Field Play Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    24% complete

This project will reconstruct the asphalt play fields in Travers Park and Staunton Field, and construct a plaza within the 78th Street right-of-way.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: October 2015
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: August 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $6,446,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/17/2018