Travers Park and Staunton Field Play Field Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the asphalt play fields in Travers Park and Staunton Field, and construct a plaza within the 78th Street right-of-way.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: February 2014
Projected Completion Date: October 2015
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: August 2017
Adjusted Completion Date: November 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Source: Mayoral