Mannahatta Park Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the fountain and lighting damaged by Hurricane Sandy in Mannahatta Park.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2017
Adjusted Completion Date: March 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Mannahatta Park, Manhattan
Wall, Water and South Streets

 

Project Staff

Project Liaison: Steve Simon