Glick Park Electrical Repairs (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will perform electrical repairs at Glick Park due to damages from Hurricane Sandy.

Project Update: Bids have been opened and are being evaluated.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: January 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Adjusted Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Federal

Location

East River Esplanade, Manhattan
Along the East River, between East 36th and East 38th Streets, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/16/2018