Washington Square Park Perimeter Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter sidewalks at Washington Square Park.

Project Timeline

Design

Start Date: February 2014
Projected Completion Date: March 2014
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: June 2015

Construction

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: October 2016

Understand how we build parks.

Funding

Total Funding: $1,375,000
Funding Source: Mayoral

Location

Washington Square Park, Manhattan
Waverly Place, West 4th Street, University Place and Macdougal Street, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/04/2017

Was this information helpful?