Carmansville Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Carmansville Playground.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: July 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: August 2016

Construction

Start Date: September 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $2,449,000
Funding Sources:
  • Mayoral
  • City Council

Location

Carmansville Playground , Manhattan
Amsterdam Avenue between West 151st and West 152nd Streets, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/19/2018