Carmansville Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Carmansville Playground.
Project Timeline
Design
Start Date: November 2013
Projected Completion Date:
July 2015
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
September 2016
Completion
Date:
August 2016
Construction
Start Date: September 2016
Projected Completion Date:
December 2017
Completion
Date:
December 2017