Bennerson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Samuel N. Bennerson Playground.

Project Timeline

Design

Start Date: December 2013
Projected Completion Date: June 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: November 2016

Construction

Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: January 2018

Understand how we build parks.

Funding

Total Funding: $2,508,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Samuel N. Bennerson 2nd Playground , Manhattan
West 64th Street between Amsterdam Avenue and West End Avenue, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/07/2018