Jackie Robinson Recreation Center Exterior Facade & Roofing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the exterior facades and the roof of the Jackie Robinson Recreation Center.

Project Update: The contract is registered.

Project Timeline


Start Date: April 2014
Projected Completion Date: May 2014
Completion Date: June 2016


Start Date: June 2016
Projected Completion Date: February 2017
Completion Date: February 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council


Jackie Robinson Park , Manhattan
Bradhurst Avenue between West 145th and West 147th Streets, Manhattan


Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/16/2018