Jackie Robinson Recreation Center Exterior Facade & Roofing Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the exterior facades and the roof of the Jackie Robinson Recreation Center.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: May 2014
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: February 2017
Adjusted Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Jackie Robinson Park, Manhattan
Bradhurst Avenue between West 145th and West 147th Streets, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/18/2018