Jackie Robinson Recreation Center Exterior Facade & Roofing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    7% complete

This project will reconstruct the exterior facades and the roof of the Jackie Robinson Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: May 2014
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: February 2017
Completion Date: February 2018

Construction

Start Date: March 2018
Projected Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Sources:
  • Mayoral
  • City Council

Location

Jackie Robinson Park , Manhattan
Bradhurst Avenue between West 145th and West 147th Streets, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/21/2018