Chelsea Recreation Center Locker Room Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the men's and women's locker rooms at the Chelsea Recreation Center.
Project Timeline
Design
Start Date: October 2014
Projected Completion Date:
October 2015
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
October 2017
Completion
Date:
June 2018
Construction
Start Date: September 2018
Projected Completion Date:
March 2020
Completion
Date:
March 2020