Hinton Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the northern and southern portions of Hinton Park.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: November 2015

Construction

Start Date: November 2015
Projected Completion Date: November 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $1,208,000
Funding Source: City Council

Location

Hinton Park , Queens
Bounded by 113th and 114th Streets and 34th and 37th Avenues

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/19/2019