Bronx Park Adult Fitness Equipment Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct adult fitness equipment and miscellaneous site work and convert a tennis court to a basketball court in Bronx Park.

Project Timeline

Design

Start Date: January 2014
Projected Completion Date: December 2014
Completion Date: January 2015

Procurement

Start Date: January 2015
Projected Completion Date: October 2015
Completion Date: January 2016

Construction

Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: January 2017

Understand how we build parks.

Funding

Total Funding: $176,000
Funding Source: City Council

Location

Bronx Park, Bronx
Bronx Park East between Brady Avenue and Unionport Road

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project