Brooklyn and Staten Island General Roofing Systems Reconstruction (CNYG-1214MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofing systems at various parks and recreation facilities in Brooklyn and Staten Island.

Project Timeline

Design

Start Date: December 2013
Projected Completion Date: January 2014
Completion Date: November 2014

Procurement

Start Date: November 2014
Projected Completion Date: August 2015
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $2,098,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/08/2019