Manhattan Roofing Systems Reconstruction (MG-614M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct roofing systems in Manhattan.
Project Timeline
Design
Start Date: December 2013
Projected Completion Date:
January 2014
Completion Date:
March 2014
Procurement
Start Date: March 2014
Projected Completion Date:
December 2014
Completion
Date:
July 2015
Construction
Start Date: September 2015
Projected Completion Date:
September 2018
Completion
Date:
September 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
De Witt Clinton Park
, Manhattan
W. 52 St. To W. 54 St., 11 Ave. To 12 Ave. -
Fort Tryon Park
, Manhattan
Riverside Drive to Broadway, West 192 to Dyckman Streets -
John V. Lindsay East River Park
, Manhattan
Northern Extreme of Park including 2 Ballfields, Lawn Areas, Sitting Areas -
Martin Luther King, Jr. Playground
, Manhattan
Lenox Ave, W. 113 St. To W. 114 St. -
Mathews-Palmer Playground
, Manhattan
W. 45 St. Between 9 Ave. and 10 Ave. -
McCaffrey Playground
, Manhattan
West 43 Street, 8 & 9 Avenues -
Seward Park
, Manhattan
Canal St, Essex St, Jefferson St & E Broadway
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/15/2021