Joe Michael's Mile Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the southern portion of Joe Michael's Mile.
Project Timeline
Design
Start Date: June 2014
Projected Completion Date:
January 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion
Date:
August 2018