Queens General Site Work (QG-614MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, fencing, drainage, play equipment, ballfields and miscellaneous site work in Queens.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: March 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: July 2017
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $2,434,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?