Citywide Comfort Station and Facility Reconstruction (CNYG-814MA)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct comfort stations and facilities at various parks and recreation locations citywide.
Project Timeline
Design
Start Date: December 2013
Projected Completion Date:
December 2013
Completion Date:
October 2014
Procurement
Start Date: October 2014
Projected Completion Date:
June 2015
Completion
Date:
March 2016
Construction
Start Date: May 2016
Projected Completion Date:
May 2019
Completion
Date:
May 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Bayview Playground, Brooklyn
S/s Seaview Av Opp E 99 St -
El Shabazz Playground, Brooklyn
Reid Av, Macon and Macdonough Sts -
People's Park, Bronx
E. 141 St. bet. Brook Ave. and St Ann's Ave. -
Walter Gladwin Park, Bronx
Cross Bronx Expressway, Third Avenue, Tremont & Arthur Avenues
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 07/05/2022