NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Citywide Reconstruction of Deteriorated Electrical Systems (CNYG-614M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    26% complete

This multisite contract will reconstruct deteriorated electrical systems at various parks and recreation pool facilities citywide.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2013
Projected Completion Date: December 2013
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source: Mayoral

Locations

  • Betsy Head Park, Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • Bushwick Playground, Brooklyn
    Flushing Ave. between. Beaver St. and Garden St.
  • Fox Playground, Brooklyn
    Avs H and I, E 54 To E 55 Sts
  • John Jay Park, Manhattan
    East 76-East 78 Streets, Cherokee Place
  • Lyons Pool, Staten Island
    Pier 6, Victory Blvd. & Murray Hulbert Ave.
  • The Big Park, Staten Island
    Grandview Ave., at Continental Pl.
  • Thomas Greene Playground, Brooklyn
    Nevins St., 3 Ave., bet. De Graw St. and Douglas St.
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/04/2017

Was this information helpful?