East River Park Fireboat House Reconstruction and ADA Entrance Ramp Installation

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct an ADA entrance ramp and install solar panels at the Fireboat House in East River Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: May 2015
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Sources:
  • Borough President
  • City Council

Location

John V. Lindsay East River Park, Manhattan
Grand Street between the FDR Drive and the East River, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017