East River Park Fireboat House Reconstruction and ADA Entrance Ramp Installation

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct an ADA entrance ramp and install solar panels at the Fireboat House in East River Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: May 2015
Adjusted Completion Date: June 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Borough President
  • City Council

Location

John V. Lindsay East River Park , Manhattan
Grand Street between the FDR Drive and the East River, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project