Cedar Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct the comfort station in Cedar Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $723,000
Funding Source: Borough President

Location

Cedar Playground , Bronx
Cedar Avenue between West 179th Street and Sedgwick Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2018