Cedar Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Cedar Playground.

Project Update: The contract was submitted to the Comptroller’s office for registration.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Adjusted Completion Date: May 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Borough President

Location

Cedar Playground , Bronx
Cedar Avenue, between West 179th Street and Sedgwick Avenue, Borough of the Bronx, Block/Lot-2881/100

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project