Sumner Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Sumner Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: December 2014
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: January 2017

Construction

Start Date: April 2017
Projected Completion Date: September 2018
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $5,154,000
Funding Sources:
  • Mayoral
  • City Council

Location

Sumner Playground , Brooklyn
Throop Avenue between Park Avenue and Myrtle Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2018